Building diary

We will keep you informed about the Construction of our new logistics hall up to date.

17 June 2026
Installation of the loading ramps

The two loading bays have been installed. The first shipments will take place later this month.

16 June 2026
Completion of the interior fit-out

The interior fit-out of the new warehouse has been completed. The new warehouse is now ready for use. The first pallets will be stored there very soon.

24 April 2026
Construction of the logistics office

The interior work is taking shape. In addition to the actual warehouse function, our new hall will also be equipped with a new logistics office.

17 April 2026
Laying the screed

Another milestone in the interior work has been reached: the screed has been laid and levelled in the new warehouse to create the optimum conditions for later use.

10 April 2026
Floor preparation

Before laying the screed, the necessary preparatory work was first carried out indoors. This included backfilling and compacting the substrate and laying a film as a separating and protective layer.

06 February 2026
Roof assembly in full swing

Roof assembly is progressing rapidly on our construction site. The trapezoidal sheets are currently being fitted precisely with the help of a crane, successfully completing a key construction phase.

moreToBuilding diary