Building diary

We will keep you informed about the Construction of our new logistics hall up to date.

06 February 2026
Roof assembly in full swing

Roof assembly is progressing rapidly on our construction site. The trapezoidal sheets are currently being fitted precisely with the help of a crane, successfully completing a key construction phase.

05 February 2026
Attaching the side panels

After completion of the supporting structure, the side walls of Hall 1 were installed in the next construction phase. At the same time, the basic pipes for the waste water in this area were completed.

20 January 2026
Assembly of the supporting structure

The load-bearing supports were professionally installed. The main and secondary roof beams were then installed, completing the primary construction of Hall 1 on schedule.

30 October 2025
Erection of the concrete firewall

The construction of the warehouse began with the erection of the concrete firewall. This is a concrete cavity wall, which was prefabricated in the precast plant with inner and outer shells and filled with in-situ concrete. Each element is 8.20 m high, 2.50 m wide and weighs around seven tonnes.

21 October 2025
Start of construction of the new warehouse

The earthworks have been successfully completed. Now that the foundations have been laid, the actual construction of the warehouse can begin.

20 August 2025
Earthworks

The demolition of the old buildings has been successfully completed and the earthworks are in full swing.