The interior work is taking shape. In addition to the actual warehouse function, our new hall will also be equipped with a new logistics office.
Another milestone in the interior work has been reached: the screed has been laid and levelled in the new warehouse to create the optimum conditions for later use.
Before laying the screed, the necessary preparatory work was first carried out indoors. This included backfilling and compacting the substrate and laying a film as a separating and protective layer.
Roof assembly is progressing rapidly on our construction site. The trapezoidal sheets are currently being fitted precisely with the help of a crane, successfully completing a key construction phase.
After completion of the supporting structure, the side walls of Hall 1 were installed in the next construction phase. At the same time, the basic pipes for the waste water in this area were completed.
The load-bearing supports were professionally installed. The main and secondary roof beams were then installed, completing the primary construction of Hall 1 on schedule.