We will keep you informed about the Construction of our new logistics hall up to date.

24 April 2026
Construction of the logistics office

The interior work is taking shape. In addition to the actual warehouse function, our new hall will also be equipped with a new logistics office.

17 April 2026
Laying the screed

Another milestone in the interior work has been reached: the screed has been laid and levelled in the new warehouse to create the optimum conditions for later use.

10 April 2026
Floor preparation

Before laying the screed, the necessary preparatory work was first carried out indoors. This included backfilling and compacting the substrate and laying a film as a separating and protective layer.

06 February 2026
Roof assembly in full swing

Roof assembly is progressing rapidly on our construction site. The trapezoidal sheets are currently being fitted precisely with the help of a crane, successfully completing a key construction phase.

05 February 2026
Attaching the side panels

After completion of the supporting structure, the side walls of Hall 1 were installed in the next construction phase. At the same time, the basic pipes for the waste water in this area were completed.

20 January 2026
Assembly of the supporting structure

The load-bearing supports were professionally installed. The main and secondary roof beams were then installed, completing the primary construction of Hall 1 on schedule.

moreToBuilding diary