Our new logistics centre

Construction work is now complete. Come and see our new logistics centre.

Take a look inside our new logistics centre

Building diary

19 October 2026
Optimisation of internal transport routes

With the new logistics hall, we are laying the foundations for more efficient internal logistics processes. Thanks to the optimised layout of the storage areas and shorter transport routes, pallets can be moved more quickly and with greater precision. This reduces internal transport costs, improves material flows and ensures smoother day-to-day operations in the warehouse.

17 August 2026
Start of camp occupancy

The first storage areas are already filled with pallets. The new storage capacity is now being put to active use.

13 July 2026
Completion of the new logistics hall

We are delighted to announce the successful completion of our new logistics centre. With this additional storage capacity, we are creating more space and optimising our operational processes.

17 June 2026
Installation of the loading ramps

The two loading bays have been installed. The first shipments will take place later this month.

16 June 2026
Completion of the interior fit-out

The interior fit-out of the new warehouse has been completed. The new warehouse is now ready for use. The first pallets will be stored there very soon.

24 April 2026
Construction of the logistics office

The interior work is taking shape. In addition to the actual warehouse function, our new hall will also be equipped with a new logistics office.

moreToBuilding diary